Passenger services on the main western rail line in the Blue Mountains have resumed following December’s freight train derailment.
Deputy Premier and Minister for Regional NSW Paul Toole said the 3.49am service from Lithgow to Sydney will be the first passenger train through now that repairs to the track between Lawson and Linden have been completed.
“The NSW Government prioritised getting this line reopened before the end of school holidays, because we know how important it is for commuters and families to have reliable train services through the Blue Mountains,” Toole said.
“Crews have put in a mammoth effort to get this line reopened, replacing 18.1 kilometres of damaged track, installing more than 15,000 new sleepers and 24,000 tonnes of ballast, and replacing or repairing 92 pieces of signalling equipment.
Related stories:
- $500M boost to tackle flood-damaged roads across NSW
- $50M funding boost announced for NSW road repairs
- $70M additional funding for NSW’s Avoca Drive upgrades
“I thank local residents for their patience; their cooperation has allowed us to get the job done as quickly as possible.”
Minister for Regional Transport and Roads Sam Farraway said Transport for NSW and Sydney Trains had to rebuild the entire damaged track in extremely difficult terrain, which required detailed planning and specialist engineering expertise.
“The Blue Mountains rail line is a critical freight corridor linking east with west,” Farraway said.
“We worked closely with the freight industry during the repair period, opening the adjacent track to allow for diesel freight train movements across this critical supply chain.
“It’s great news that following the completion of repairs, full freight access will resume on the Blue Mountains line, as well as intercity and regional passenger train services.
“I’d like to thank our rail freight industry, passengers and the local community for their patience and understanding while the repairs were undertaken. I would also like to acknowledge the professionalism of the engineering and track work teams who completed the significant repairs to the rail corridor.”
More than 140 frontline staff worked each shift during the repair process, with a total of 420 staff working within each 24-hour window.