How Fulton Hogan applied innovative technology to stabilise hazardous rock face

Over the years the steep rock face had caused road closures.

When New Zealand contractor Fulton Hogan was awarded a contract to remediate a steep unstable rock face overlooking the Port of Otago, it was faced with a number of challenges to deliver the project safely, within a tight budget, and in a highly visible location.

The project, known as the Flagstaff Hill Earthworks, was to stabilise a steep hazardous rock face next to the Port.

Also known as Observation Point, reclamation of areas of the port during the 1990s had resulted in an unstable rock face, with several slips, as well as rocks and boulders falling to the road below.

For the past 20 years, half the roadway at the foot of the face has been battered off with safety fencing to protect public roads and walkways.

The area is one of outstanding beauty, with views to Otago Harbour’s historic Quarantine and Goat Islands, and across to the Otago Peninsula.

A KiwiRail line for freight and daily passenger services during the cruise ship season runs adjacent to the site, while both locals and tourists use the road and tracks below for recreation.

Over the years, slips have caused closure of the road, while frequent rock falls and boulders have come down the slope.

In about 2000, to minimise risks, Port Otago installed a shipping container wall across half of the road, along with additional safety catch fencing to protect the public. At the same time, an adjacent log yard storage and handling area was reduced, to allow the public road to use part of the Port’s land for access.

The unstable nature of the face meant daily inspections of the road had to be carried out since the 1990s works. Slips, boulders and rock falls had to be removed on an all-too-regular basis.

Consulting engineers WSP Opus were awarded a design contract to assess the underlying geology and develop a design for a cut slope with benches to remove the risk of further slips and rock falls in the area. The result of the design was the planned removal of 47,735 cubic metres of material.

Fulton Hogan successfully tendered for the works, which commenced in the winter of 2019, completing the project in the four months to October 2019.

Fulton Hogan successfully tendered for the removal of 47,735 cubic metres of material.

According to Grant Sime, Fulton Hogan’s senior project delivery manager in Dunedin, the contract scope was to work at height on an unstable rock face and strip off over 47,000 cubic metres of clay and rock, and safely remove all the material from site.

“Before we would work out where and how to start the physical work, the entire site needed to be accurately surveyed,” Sime said.

“With existing gradients of 70 per cent and greater, combined with the instability of the ground, putting people on the slope face would have been extremely dangerous.

“Using our own in-house surveying team, and external subcontractor Jared Reeves of Overview Surveying, we carried out a point cloud survey using a drone to understand what we were up against.”

The pre-start drone survey was mapped against the required finished batter of 35 per cent, along with three, five-metre wide benches at the top of the slope, so that the exact quantities of material to be excavated were known.

Given the safety and operational challenges of excavating on such a steep, unstable slope, Fulton Hogan sought input from excavator operators Ray Ta Huna and Kevin Patrick on how best to proceed.

Sime described Ray and Kevin as two of the best operators in the region.

“It’s simple,” Ray said. “When you are loading out from a digger, you sit on top of the material and load out while your mound comes down gradually.”

Sime said this response gave Fulton Hogan the basis for how to proceed, knowing the company had full engagement of its expert operators.

“Together we developed a plan.”

The in cab view of the screen on the Komatsu PC201LCi-10 intelligent Machine Control.

With the drone survey having provided a highly accurate 3D overview of the existing site, and WSP Opus providing a 3D model of the required final design, making use of an excavator fitted with precision GPS-based machine control was the solution to this challenge.

Fulton Hogan purchased a Komatsu PC210LCi-10 intelligent Machine Control (iMC) excavator specifically for this project. Based around Topcon’s precision machine control capabilities, fully factory integrated within the machines, iMC allows earthworks to be carried out to millimetre-level accuracy.

“Having integrated Machine Control on this excavator was magic,” Sime said.

“Not having to set out pegs using manual survey methods improved efficiency tenfold. And because we didn’t have to have a surveyor on the ground, it was much safer.

“In that type of environment, we had no option but to start at the top and work down, and there was no going back.

“And the end result was without a doubt the best batter slope I ever been associated with,” he said. “It wasn’t just a simple slope either; it was benched at the top, then battered and curved around to follow the line of the point.”

The designs for the batter were provided to Fulton Hogan electronically, then downloaded to the iMC excavator, so at all times it was working to the client’s designs.

“In addition, the client accepted the as-builts coming out of the machine,” Sime said.

“Then, when we completed the 47,000 m3 material removal, we were between 80 to 100 m3 out, compared with the original design. It was so close, the client was just blown away. We are very proud of how close we got; in terms of that volume of material, it was nothing,” Sime said.